For objects with a small amount of ventilation work and capital repairs, abbreviated The project of work production is the basic guide for the organization and production of installation work at the facility. Project of work production helps to plan all the preparatory work, including the execution of orders for air ducts and applications for ventilation equipment and materials, to determine the storage locations of bulky ventilation parts. The project of work production contributes to the uninterrupted conduct of installation work, improving the quality of installation.

7.2. Acceptance of the object for installation work

Prior to the start of installation work on the object or on its part, a list of individual types of construction works, the performance of which is necessary for the subsequent installation of ventilation systems, and the timing of their execution must be agreed between the representatives of the installation organization and the general contractor.

Such works include:

1) installation of foundations, platforms and other supporting structures for ventilation equipment;

2) installation of walls and partitions in ventilation chambers, as well as ceilings, if the project of work production does not provide for the supply of ventilation equipment through the top of the chambers;

3) installation of embedded parts provided for by the project in ventilation chambers for connecting ventilation equipment and along the route of systems for fixing air ducts;

4) installation of horizontal and vertical mounting openings for the supply of ventilation equipment and ducts from an on-site warehouse to the place of their installation;

5) installation of walls and ceilings in the places of laying air ducts;

6) plastering and painting of walls, ceilings and partitions in the places of laying air ducts and installing air distributors;

7) punching holes in places where air ducts pass through walls, ceilings and partitions, if they are not left during the construction of the building;

8) installation of reinforced concrete cups on floors in places of passage of ventilation shafts and installation of roof fans;

9) the device of fasteners for large-sized air ducts and platforms for cyclones, scrubbers, filters, etc.;

10) the device of ventilation ducts in construction (brick, concrete);

11) glazing of window openings and lanterns

12) cleaning of ventilation work sites from construction debris.

After performing these works on the entire object, the object is accepted under a bilateral act for installation. It is especially necessary to carefully prepare the rooms of the ventilation chambers, where all construction work (except clean floors and final painting) must be carried out and the lifting devices provided for by the project for the operation and repair of ventilation equipment must be installed. For the passage of air ducts through building structures, the holes in them must be 150 mm larger than the diameter of a round or the dimensions of the sides of a rectangular air duct.

By the time the installation works begin, the general contractor must provide the installation team with:

a) cabins for workers, a room for a workshop and a storeroom, open storage areas and sheds for storing air ducts, ventilation equipment and products in the area of operation of vehicles;

b) supply of electricity, water and heat during the cold period for the production of works and for domestic premises;

c) vertical and horizontal on-site transport;

d) electric lighting in places where ventilation works are performed;

e) fire and guard protection.

To perform installation work directly on the site, it is necessary to have the following technical documentation:

1) two copies of working drawings;

2) a set of installation drawings or sketches for all ventilation systems;

3) a project for the production of works with standard technological maps;

4) the list of ventilation equipment and materials supplied by the customer (non-standard equipment, alloy steel, etc.);

5) the act of acceptance of the object for installation.

After acceptance of the object for installation, mounting devices (ladders, towers, traverses, blocks, scaffolds, etc.), mounting mechanisms, electrified tools, welding equipment and tool kits are delivered to the object.

7.3. Installation design

Air ducts of ventilation systems are manufactured only according to installation drawings or sketches. Installation drawings are carried out on the basis of working drawings of ventilation systems.

  • Читать дальше
  • 1
  • ...
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17

Ебукер (ebooker) – онлайн-библиотека на русском языке. Книги доступны онлайн, без утомительной регистрации. Огромный выбор и удобный дизайн, позволяющий читать без проблем. Добавляйте сайт в закладки! Все произведения загружаются пользователями: если считаете, что ваши авторские права нарушены – используйте форму обратной связи.

Полезные ссылки

  • Моя полка

Контакты

  • chitat.ebooker@gmail.com

Подпишитесь на рассылку: